Site Works
Sims Metals, Stage 3
CLIENT
Sims Metals
LOCATION
Christchurch
COMPLETED
In progress, due September 2027
SCOPE
Concrete slabs and stormwater drainage
Concrete poured
1,080 m³
01 / Overview
Sealing a working yard
in concrete.
02 / The work
Stage 3 is sealing the whole Sims Metals compound with concrete slabs and new drainage. It is about 60% complete and due to finish in September 2027.
Johnston Civil is building the concrete slabs for the entire Sims Metals compound. To seal the surface, new underground stormwater pipes and manholes, and above-ground tanks, are being installed to drain both the yard and the buildings.
So far the work has excavated more than 4,000 m², moved about 2,000 m³ of earth, installed around 210 m of drainage and poured 1,080 m³ of concrete. Earlier stages involved smaller amounts of earthmoving and concrete.