Specialist Works
Heathcote River Dredging
CLIENT
Citycare, for Christchurch City Council
LOCATION
Lower Heathcote River, Christchurch
COMPLETED
February 2020
SCOPE
River dredging, Stages 1 and 2
Silt removed
46,000 t
01 / Overview
Clearing decades
of silt from the river.
02 / The work
Johnston Civil dredged the lower Heathcote River for Citycare from October 2018 to early 2020, removing about 46,000 tonnes of silt across Stages 1 and 2.
The work was part of Christchurch City Council's Land Drainage Recovery Programme. Regular dredging had stopped in the mid-1980s and the earthquakes had added more silt, so the river needed clearing to carry stormwater again.
Stage 2 ran from Radley Street to Opawa Road and was split into two phases around the whitebait spawning season. Our 30-tonne amphibious excavator, fitted with GPS and a 16 m long-reach arm, worked from the water and loaded a barge that was winched to the bank for unloading.
Every machine ran on biodegradable hydraulic oil. Our workshop built an extra arm so the excavator could dredge beneath the Brougham Street, rail and Opawa Road bridges, and the team reinstated each load-out point on the bank as the work moved upstream.