Oakvale Subdivision
CLIENT
Carter Group
LOCATION
Kennedys Bush Road, Christchurch
COMPLETED
August 2023 (Phase 1)
SCOPE
Subdivision civil works, Phases 1 and 2
Lots (Phase 1)
218
01 / Overview
A new neighbourhood
built in two phases.
02 / The work
Johnston Civil delivered Phase 1 of Oakvale, 218 lots in a single stage completed in August 2023, then returned to build Phase 2.
Phase 1 ran from December 2021 to August 2023. It included over 100,000 m³ of earthworks, 14,500 m² of TC3 rafts, stormwater drains up to 700 mm, a pressure sewer system and 8 km of service trenching, plus a 700 m frontage upgrade and new roundabout on Kennedys Bush Road.
Glovers Drain ran through the middle of the site and had to stay live. A new drain was built alongside it under a strict erosion and sediment control plan, while well points and pumps dewatered trenches up to 2.8 m deep through the wettest July on record in 2022.
Phase 2 added bulk earthworks, stormwater ponds, pressure sewer, water, power and fibre, roads, kerbs and footpaths. It moved 43,950 m³ of earth off site and laid 1,446 m of kerb and 6,640 m² of asphalt, leaving fully serviced sections ready to build on.